Under construction

ESTIQUE B WINGMahaRERA P52100032999

by KHANDVE PATIL CONSTRUCTIONS

127/4 PLUS 5/2/1 OLD , 127/4A PLUS 5/2/1 NEW PLUS 131/1B/2/7 PLOT NO A PLUS B PLUS C PLUS D, BANER, 411045

Jun 2024
Possession
81.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 81.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.

Official RERA facts

Registration
P52100032999
Status
New
Stage
Certificate Signed
Possession
June 2024originally December 2023
Construction
81.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2022
Floors
8

Buyer community

Connect with other buyers and owners of ESTIQUE B WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ESTIQUE B WING. Real notes from real buyers beat any brochure.

Start a discussion