Under construction

Windsor County Phase IV Wing IMahaRERA P52100034251

by Windsor Shelters

39/24 part, Ambegaon Bk., 411046

Sept 2025
Possession
90.9%
Built
0
Complaints
132
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100034251
Status
New
Stage
Certificate Signed
Possession
September 2025
Construction
90.9% complete
Units sold
111 of 132

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lighting95%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station99%
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Mar 2022
Floors
14
Unit mix
119 res ยท 13 comm
Architect
Viinod Khanjode

Buyer community

Connect with other buyers and owners of Windsor County Phase IV Wing I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Windsor County Phase IV Wing I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.