VASANTSHREEMahaRERA P52100045708
Plot No.30 S.No.28 Hissa No.4, Chittavihari Society, 411043
Jun 2025
Possession
90%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 90%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2025 per the RERA filing.
Official RERA facts
- Registration
- P52100045708
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2025originally December 2024
- Construction
- 90% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Sewerage (Chamber, Lines, Septic Tank , STP)done
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started
Open Parkingnot started
Entrance gatedone
Entrance gatenot started
Entrance gatedone
UGWTdone
UGWTnot started
Building & registration
- RERA registered
- Jun 2022
- Floors
- 8
Buyer community
Connect with other buyers and owners of VASANTSHREE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VASANTSHREE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.