Under construction

RATNAPRABHAMahaRERA P52100045880

by ASHWAMEDH SPACES PRIVATE LIMITED

Plot no 67 CTS 850, Kothrud, 411038

Feb 2026
Possession
90.5%
Built
1
Complaints
52
Units
High risk
  • Possession date passed. The proposed possession date (Feb 2026) has passed with construction at 90.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2026 per the RERA filing.

Official RERA facts

Registration
P52100045880
Status
New
Stage
Certificate Signed
Possession
February 2026originally June 2025
Construction
90.5% complete
Units sold
22 of 52

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2022
Floors
16
Unit mix
52 res ยท 0 comm
Architect
GOHAD ARCHITECTS

Buyer community

Connect with other buyers and owners of RATNAPRABHA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RATNAPRABHA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.