Lodha Pune NIBM Project- Tower 7,8 and 9

by Lodha Developers Limited

28/1A(P), 28/1B(P), 28/2(P), 28/3, 28/4, 28/6, 28/5A, 36/7+8B(P), 36/11, 36/14, 36/16, 36/8A(P), 36/9/1, 36/9/2(P), 36/10(P), 36/15, 36/13, Haveli, 411060

โ€”
Possession
โ€”
Built
2
Complaints
โ€”
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100046081
Status
โ€”
Stage
โ€”
Possession
โ€”
Construction
โ€”
Units sold
โ€”

RERA complaint record2 records

  • ComplaintCC1260181928 Mar 2026
    SAGAR GIRIDHARILAL KARMANI vs Lodha Developers Limited
  • ComplaintCC1260180028 Mar 2026
    SNEHA JOYCHAND KARMANI vs Lodha Developers Limited

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths25%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2022
Floors
29
Unit mix
314 res ยท 0 comm
Architect
Pradeepmkamble and associates

Buyer community

Connect with other buyers and owners of Lodha Pune NIBM Project- Tower 7,8 and 9 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Lodha Pune NIBM Project- Tower 7,8 and 9. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.