Under construction

KK Mangalam EmeraldMahaRERA P52100046280

by Shah Associates & Properties

45/1 Rahatani, Rahatani, 411017

Oct 2026
Possession
84.4%
Built
1
Complaints
82
Units
Caution
  • Possession delayed ~1 yr. Originally promised May 2025, now proposed Oct 2026 per the RERA filing.

Official RERA facts

Registration
P52100046280
Status
New
Stage
Certificate Signed
Possession
October 2026originally May 2025
Construction
84.4% complete
Units sold
49 of 82

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Street Lightingnot started
Water conservation /Rain water harvesting70%
Electrical meter room, sub-station, receiving station70%

Building & registration

RERA registered
Jun 2022
Floors
7
Unit mix
61 res ยท 21 comm
Architect
Architect Vipul V Pagariya

Buyer community

Connect with other buyers and owners of KK Mangalam Emerald โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KK Mangalam Emerald. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.