GOLDEN COURTMahaRERA P52100046952

by Silverleaf landmarks llp

12/1/2 12/1/3 12/1/4 12/2 12/3A 12/3B 12/4 12/5A/1 12/5B 12/6/1 12/7 12/8 12/12/1 12/12/3 13/1/2/1, UNDRI, 411060

Jun 2027
Possession
78.2%
Built
0
Complaints
65
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100046952
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2025
Construction
78.2% complete
Units sold
56 of 65

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Street Lightingdone
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Sept 2022
Floors
7
Unit mix
0 res ยท 65 comm
Architect
Group Consultants

Buyer community

Connect with other buyers and owners of GOLDEN COURT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GOLDEN COURT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.