27 GRAND RESIDENCES- TOWER 2MahaRERA P52100047314

by Majestique Luxury Homes LLP

27/1/2/3, BALEWADI, 411045

Dec 2027
Possession
75.9%
Built
0
Complaints
128
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100047314
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
75.9% complete
Units sold
87 of 128

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Planting25%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water25%
Solid Waste Management And Disposal52%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2022
Floors
40
Unit mix
128 res ยท 0 comm

Buyer community

Connect with other buyers and owners of 27 GRAND RESIDENCES- TOWER 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 27 GRAND RESIDENCES- TOWER 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.