Under construction

Millennium EmeraldMahaRERA P52100047332

by MILLENNIUM PROPERTIES

181/2 and 181/3, Wakad, 411057

Dec 2026
Possession
73.6%
Built
1
Complaints
113
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100047332
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
73.6% complete
Units sold
111 of 113

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2022
Floors
12
Unit mix
112 res ยท 1 comm
Architect
Vastushaili Architects

Buyer community

Connect with other buyers and owners of Millennium Emerald โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Millennium Emerald. Real notes from real buyers beat any brochure.

Start a discussion