204 BLUE PARADISEMahaRERA P52100047531
SR.NO 204/7/1+204/7P+204/6A+204/4+204/1+204/2, Baner, 411045
Jun 2026
Possession
76.4%
Built
0
Complaints
77
Units
High risk
- Possession delayed ~1 yr. Originally promised Mar 2025, now proposed Jun 2026 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 76.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100047531
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026originally March 2025
- Construction
- 76.4% complete
- Units sold
- 36 of 77
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started
Building & registration
- RERA registered
- Nov 2022
- Floors
- 16
- Unit mix
- 66 res ยท 11 comm
Buyer community
Connect with other buyers and owners of 204 BLUE PARADISE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching 204 BLUE PARADISE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.