Under construction

Park Infinia - B1 and B2MahaRERA P52100047895

by Kumar Properties and Real Estate Pvt. Ltd.

214P 220P 221P, Hadapsar, 412308

Oct 2025
Possession
78.7%
Built
0
Complaints
94
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 78.7%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2025 per the RERA filing.

Official RERA facts

Registration
P52100047895
Status
New
Stage
Certificate Signed
Possession
October 2025originally July 2025
Construction
78.7% complete
Units sold
93 of 94

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting95%
Energy managemcnt95%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station63%
Aggregate area of recreational Open Spacedone
Open Parkingnot started

Building & registration

RERA registered
Dec 2022
Floors
13
Unit mix
94 res ยท 0 comm
Architect
Vishal J Deshpande
Public authority
PMC

Buyer community

Connect with other buyers and owners of Park Infinia - B1 and B2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Park Infinia - B1 and B2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.