Building B2 Eon HomesMahaRERA P52100048176
by Hinjawadi Infradevelelopment Private Limited
Plot R-3/1 Part, Hinjawadi Phase III, 411057
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100048176
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 13.6% complete
- Units sold
- 143 of 183
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2022
- Floors
- 24
- Unit mix
- 183 res ยท 0 comm
Buyer community
Connect with other buyers and owners of Building B2 Eon Homes โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Building B2 Eon Homes. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.