WELLINGTON C - DMahaRERA P52100048477

by PRIDE BUILDERS LLP

S NO 129/2, 131/1 & 2, 135/2 TO 6, PCMC, 412015

Sept 2026
Possession
100%
Built
0
Complaints
264
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52100048477
Status
New
Stage
Certificate Signed
Possession
September 2026
Construction
100% complete
Units sold
259 of 264

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting90%
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingdone

Building & registration

RERA registered
Jan 2023
Floors
26
Unit mix
264 res ยท 0 comm
Architect
PATIL & BUGADE ASSOCIATES

Buyer community

Connect with other buyers and owners of WELLINGTON C - D โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching WELLINGTON C - D. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.