Under construction

172W Inclusive HousingMahaRERA P52100049412

by Vilas Javdekar Lifestyle Developers Pvt. Ltd.

172 1 B Part and 172 1 C, Wakad, 411057

Jun 2026
Possession
68.2%
Built
0
Complaints
21
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 68.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Official RERA facts

Registration
P52100049412
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
68.2% complete
Units sold
20 of 21

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station70%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2023
Floors
15
Unit mix
21 res ยท 0 comm
Architect
Prajakta Yadav

Buyer community

Connect with other buyers and owners of 172W Inclusive Housing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 172W Inclusive Housing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.