Under construction

ANANTAM SKYONEMahaRERA P52100049675

by RAJSHREE LANDMARK LLP

GAT NO 205 (P) 206(P) DUDULGAON, DUDULGAON, 412105

Oct 2026
Possession
81.8%
Built
0
Complaints
100
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.

Official RERA facts

Registration
P52100049675
Status
New
Stage
Certificate Signed
Possession
October 2026originally December 2025
Construction
81.8% complete
Units sold
94 of 100

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2023
Floors
16
Unit mix
89 res ยท 11 comm
Architect
ARCON ASSOCIATES

Buyer community

Connect with other buyers and owners of ANANTAM SKYONE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANANTAM SKYONE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.