Under construction

West 9 Buissness ArcMahaRERA P52100050051

by S R K Realty & AS Developers

Sr No 71/1/2 (P), CTS No 2387, Sangvi, 411027

Dec 2027
Possession
53.6%
Built
1
Complaints
74
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100050051
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
53.6% complete
Units sold
14 of 74

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Mar 2023
Floors
8
Unit mix
0 res ยท 74 comm
Architect
Spot Consultants

Buyer community

Connect with other buyers and owners of West 9 Buissness Arc โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching West 9 Buissness Arc. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.