PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ADITYA ENCLAVEMahaRERA P52100050290

by RAKHI PANKAJ CHOPADA

PAP 18 TO PAP 32, PUNE, 411057

Mar 2027
Possession
75%
Built
0
Complaints
128
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52100050290
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
75% complete
Units sold
11 of 128

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2023
Floors
9
Unit mix
40 res ยท 88 comm
Architect
SUDHIR PATIL & ASSOCIATES

Buyer community

Connect with other buyers and owners of ADITYA ENCLAVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ADITYA ENCLAVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.