Under construction

Vallabh Co-op Housing SocietyMahaRERA P52100050438

by SRKD LANDMARK LLP

CTS NO. 968+969, FINAL PLOT NO. 395+396, PLOT NO. 38+39, SHIVAJI NAGAR-BHAMBURDA, Bhamburda, 411016

Sept 2026
Possession
63.6%
Built
0
Complaints
33
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Sept 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52100050438
Status
New
Stage
Certificate Signed
Possession
September 2026originally March 2025
Construction
63.6% complete
Units sold
16 of 33

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2023
Floors
12
Unit mix
33 res ยท 0 comm
Architect
Devendra V Dhere

Buyer community

Connect with other buyers and owners of Vallabh Co-op Housing Society โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vallabh Co-op Housing Society. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.