ARBOR VISTAMahaRERA P52100050504

by Atul Kanhaiyalal Surana

Sr. No. 71 , Hissa No. 1A/1 , Wakad, Wakad, 411057

Dec 2027
Possession
36.5%
Built
1
Complaints
172
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100050504
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
36.5% complete
Units sold
49 of 172

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2023
Floors
27
Unit mix
163 res ยท 9 comm
Architect
VK A Architecture

Buyer community

Connect with other buyers and owners of ARBOR VISTA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ARBOR VISTA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.