Under construction

Karha VastuMahaRERA P52100050777

by S J DEVELOPERS

Surve No. 9/5/6/7/1/2, PUNE, 412301

Nov 2026
Possession
34.1%
Built
0
Complaints
56
Units
High risk
  • Behind schedule. Possession is due Nov 2026 but construction is only at 34.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.

Official RERA facts

Registration
P52100050777
Status
New
Stage
Certificate Signed
Possession
November 2026
Construction
34.1% complete
Units sold
29 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Open Parkingnot started

Building & registration

RERA registered
May 2023
Floors
4
Unit mix
56 res ยท 0 comm
Architect
Gopal Sutar

Buyer community

Connect with other buyers and owners of Karha Vastu โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Karha Vastu. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.