Godrej Hillside 3MahaRERA P52100050939

by Mahalunge Township Developers Private Limited

Sr No 42/7 (p) and Sr No 42/13 (p), Mahalunge, 411045

Feb 2028
Possession
24%
Built
0
Complaints
493
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100050939
Status
New
Stage
Certificate Signed
Possession
February 2028
Construction
24% complete
Units sold
475 of 493

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
May 2023
Floors
32
Unit mix
493 res ยท 0 comm
Architect
ANA Consortium Pvt Ltd

Buyer community

Connect with other buyers and owners of Godrej Hillside 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Godrej Hillside 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.