PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MAJESTIQUE MARBELLA PHASE VIMahaRERA P52100051012

by Majestique Empire LLP

S.NO 42/1 AND 42/2/2, Haveli, 411014

Apr 2027
Possession
59.5%
Built
0
Complaints
93
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P52100051012
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
59.5% complete
Units sold
74 of 93

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
May 2023
Floors
20
Unit mix
93 res ยท 0 comm

Buyer community

Connect with other buyers and owners of MAJESTIQUE MARBELLA PHASE VI โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAJESTIQUE MARBELLA PHASE VI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.