PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AvaneeshMahaRERA P52100051029

by Ambika Nawu Buildcon

Survey No. 90/4/1/8, Baner, 411045

Apr 2027
Possession
43.2%
Built
0
Complaints
30
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Apr 2025, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 43.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P52100051029
Status
New
Stage
Certificate Signed
Possession
April 2027originally April 2025
Construction
43.2% complete
Units sold
0 of 30

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Open Parkingnot started

Building & registration

RERA registered
May 2023
Floors
4
Unit mix
30 res ยท 0 comm
Architect
Icons Associates Mr Rajendra Gaikwad

Buyer community

Connect with other buyers and owners of Avaneesh โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Avaneesh. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.