๐Ÿ—๏ธ
Under construction

SELF REDEVELOPMENT OF RAJNEEL CHSMahaRERA P52100051229

by RAJNEEL CHS LTD

S NO 28/9 CTS NO 458A, KOTHRUD, 411038

Mar 2027
Possession
90%
Built
0
Complaints
19
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52100051229
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
90% complete
Units sold
5 of 19

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting50%
Street Lighting20%
Community Buildingsnot started
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Jun 2023
Floors
8
Unit mix
19 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SELF REDEVELOPMENT OF RAJNEEL CHS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SELF REDEVELOPMENT OF RAJNEEL CHS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.