PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Hinjewadi Project-Tower 4 and 5MahaRERA P52100051280

by Lodha Developers Limited

126/1,127/3,127/4, Hinjawadi, 411057

Jun 2028
Possession
46.6%
Built
1
Complaints
400
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100051280
Status
New
Stage
Certificate Signed
Possession
June 2028
Construction
46.6% complete
Units sold
296 of 400

RERA complaint record1 record

  • ComplaintCC1250321411 Sept 2025
    Anshul Sudhir Naik vs Lodha Developers Limited

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposal70%
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2023
Floors
32
Unit mix
400 res ยท 0 comm
Architect
Pradeepmkamble and associates

Buyer community

Connect with other buyers and owners of Hinjewadi Project-Tower 4 and 5 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Hinjewadi Project-Tower 4 and 5. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.