Under construction

Green ParkMahaRERA P52100051621

by Classic Developers

Gat No. 201 and Gat No. 202, B. K. Park, Dudulgaon, 412105

May 2025
Possession
87.3%
Built
0
Complaints
28
Units
Caution
  • Possession date passed. The proposed possession date (May 2025) has passed with construction at 87.3%.

Official RERA facts

Registration
P52100051621
Status
New
Stage
Certificate Signed
Possession
May 2025originally December 2024
Construction
87.3% complete
Units sold
28 of 28

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains20%
Landscaping & Tree Planting20%
Street Lighting20%
Water conservation /Rain water harvesting20%
Energy managemcntnot started
Fire protection and fire safety requirements25%
Electrical meter room, sub-station, receiving station25%

Building & registration

RERA registered
Jun 2023
Floors
7
Unit mix
28 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Green Park โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Green Park. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.