PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

PADMA MADHAVMahaRERA P52100052040

by Vriddhi Realty Parvati LLP

PLOT NO 168, SURVEY NO 26, CTS NO 637, KOTHRUD, 411038

Dec 2025
Possession
66.8%
Built
0
Complaints
18
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 66.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P52100052040
Status
New
Stage
Certificate Signed
Possession
December 2025originally June 2025
Construction
66.8% complete
Units sold
11 of 18

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2023
Floors
7
Unit mix
18 res ยท 0 comm

Buyer community

Connect with other buyers and owners of PADMA MADHAV โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PADMA MADHAV. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.