Under construction

WELLINGTON-E-H-J-KMahaRERA P52100052379

by PRIDE BUILDERS LLP

S NO 129/2, 131/1, 2, 135/2 TO 6(P), PCMC, 412105

Dec 2027
Possession
82.7%
Built
0
Complaints
540
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100052379
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
82.7% complete
Units sold
523 of 540

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains30%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water30%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting2%
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parking30%

Building & registration

RERA registered
Aug 2023
Floors
26
Unit mix
540 res ยท 0 comm
Architect
PATIL & BUGADE ASSOCIATES

Buyer community

Connect with other buyers and owners of WELLINGTON-E-H-J-K โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching WELLINGTON-E-H-J-K. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.