SHIV MALHARMahaRERA P52100052401

by SHIV DEVELOPERS

S. No. 125/2/2A/3,4,5,6,7,8,10,23,27,31(P), Village Wakad, Taluka Mulshi, Pune, Wakad Road, 411057

Dec 2026
Possession
77.3%
Built
0
Complaints
122
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100052401
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
77.3% complete
Units sold
15 of 122

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water75%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2023
Floors
21
Unit mix
102 res ยท 20 comm
Architect
Projection Studio

Buyer community

Connect with other buyers and owners of SHIV MALHAR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIV MALHAR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.