Under construction

Akshara HarmonyMahaRERA P52100052405

by Garve Developers and Promoters

207/2/1/2P and 207/2/1/2/1 CTS No. 1451P, 1467P, 1468P, 1469 and 1470 Wakad, Wakad, 411057

Dec 2026
Possession
63.6%
Built
0
Complaints
35
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100052405
Status
New
Stage
Certificate Signed
Possession
December 2026originally March 2026
Construction
63.6% complete
Units sold
9 of 35

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Storm Water Drains20%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvesting20%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2023
Floors
8
Unit mix
35 res ยท 0 comm
Architect
ShIkay Group

Buyer community

Connect with other buyers and owners of Akshara Harmony โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Akshara Harmony. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.