Under construction

Prathamesh Co-Op Housing SocMahaRERA P52100052452

by Joshi Associates

94-8/1&8/2 +9+10/1+10/2+11+12, 95-3+4 of Final Plot No 32, Right Bhusari Colony, Kothrud, 411038

Sept 2026
Possession
75%
Built
0
Complaints
17
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Sept 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52100052452
Status
New
Stage
Certificate Signed
Possession
September 2026originally September 2025
Construction
75% complete
Units sold
12 of 17

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2023
Floors
8
Unit mix
17 res ยท 0 comm
Architect
Prasad Ingawale

Buyer community

Connect with other buyers and owners of Prathamesh Co-Op Housing Soc โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Prathamesh Co-Op Housing Soc. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.