Under construction

SAI VATIKA BLDG - EMahaRERA P52100052605

by ABHILASHA DEVELOPERS

634B PLOT NO 5 AND 6, Chankhed, 410506

Dec 2026
Possession
30.9%
Built
0
Complaints
33
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 30.9%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100052605
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
30.9% complete
Units sold
16 of 33

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths10%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Planting50%
Street Lighting50%
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2023
Floors
4
Unit mix
33 res ยท 0 comm
Architect
Kaustubh Chandrakant Babar

Buyer community

Connect with other buyers and owners of SAI VATIKA BLDG - E โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI VATIKA BLDG - E. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.