PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAMARTH RESIDENCYMahaRERA P52100052755

by D S Construction

Gat No. 242/2/A (Part), Awachat Estate, Patas Road, Awachat Estate, 413102

Aug 2027
Possession
37.2%
Built
0
Complaints
47
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2027 per the RERA filing.

Official RERA facts

Registration
P52100052755
Status
New
Stage
Certificate Signed
Possession
August 2027
Construction
37.2% complete
Units sold
26 of 47

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2023
Floors
7
Unit mix
47 res ยท 0 comm
Architect
Amit Sadanand Gaikwad

Buyer community

Connect with other buyers and owners of SAMARTH RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAMARTH RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.