Yashwin Urbo Centro - Phase 1MahaRERA P52100053194
by Vilas Javdekar Infinitee Developers Pvt. Ltd.
Plot A1, out of Survey No. 122/1, 122/1/A/3, 122/2, 122/5, 122/5/1, Wakad, 411057
Dec 2027
Possession
72.6%
Built
1
Complaints
704
Units
Caution
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100053194
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 72.6% complete
- Units sold
- 670 of 704
RERA complaint record1 record
- ComplaintCC125042653 Dec 2025Vilas Javdekar Infinitee Developers Pvt. Ltd. vs Mrs Lata Divakar Salve Mr Milind Baliram Parde and Master Varun Milind Parde through legal and natural gurdian mother Mrs Lata Divakar Salve (Allottees)Sr no 109 Disposal order for sign.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Oct 2023
- Floors
- 37
- Unit mix
- 696 res ยท 8 comm
- Architect
- Deepali Patidar
Buyer community
Connect with other buyers and owners of Yashwin Urbo Centro - Phase 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Yashwin Urbo Centro - Phase 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.