Mar 2027
Possession
71.8%
Built
0
Complaints
14
Units
Caution
- Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100053654
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2025
- Construction
- 71.8% complete
- Units sold
- 0 of 14
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply20%
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lightingnot started
Water conservation /Rain water harvesting70%
Energy managemcnt50%
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving station10%
Building & registration
- RERA registered
- Nov 2023
- Floors
- 3
- Unit mix
- 14 res ยท 0 comm
Buyer community
Connect with other buyers and owners of SWASTIK VYOM โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SWASTIK VYOM. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.