PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GEN1MahaRERA P52100053948

by BISHNOI KALAMKAR CONSTRUCTIONS LLP

Survey No 101 Hissa No 1/1P and 1/1/5, Baner, 411045

Dec 2026
Possession
65%
Built
0
Complaints
147
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100053948
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
65% complete
Units sold
76 of 147

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2023
Floors
15
Unit mix
0 res ยท 147 comm
Architect
Nilesh Saswade

Buyer community

Connect with other buyers and owners of GEN1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GEN1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.