Under construction

THE BUTTERFLYMahaRERA P52100054380

by VISHWA DEVELOPERS

543, MOSHI, 412105

Jul 2027
Possession
53.9%
Built
0
Complaints
98
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.

Official RERA facts

Registration
P52100054380
Status
New
Stage
Certificate Signed
Possession
July 2027originally July 2026
Construction
53.9% complete
Units sold
20 of 98

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2024
Floors
8
Unit mix
98 res ยท 0 comm
Architect
PRECISION ARCHITECT & PLANNER

Buyer community

Connect with other buyers and owners of THE BUTTERFLY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE BUTTERFLY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.