Under construction

100 KATRAJMahaRERA P52100054429

by PRATHAMESH ASSOCIATES

S NO 36/3B/1/3/6 AND SR NO 36/3E/1/4, GOKULNAGAR KATRAJ, 411046

Dec 2026
Possession
65.9%
Built
0
Complaints
45
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100054429
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
65.9% complete
Units sold
28 of 45

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2024
Floors
6
Unit mix
45 res ยท 0 comm
Architect
APG ARCH STUDIO

Buyer community

Connect with other buyers and owners of 100 KATRAJ โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 100 KATRAJ. Real notes from real buyers beat any brochure.