Audumbar Green A WingMahaRERA P52100054752
S. No./Gat No. 27/1A/1 (P), Near Nimbalkar Nagar, Opp to Tata Steel Yard, Tathawade, Tal Mulshi, Dist. Pune 411033, Near Nimbalkar Nagar, Tathwade, 411033
- Behind schedule. Possession is due Oct 2026 but construction is only at 27.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100054752
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2026originally April 2026
- Construction
- 27.3% complete
- Units sold
- 0 of 35
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
RAMESH MAHADU KUMBHAR, SURESH MAHADU KUMBHAR, SOMNATH MAHADU KUMBHAR
Possession extension history
- EA01062621178Revised to October 2026
The project could not be completed within the stipulated validity period due to circumstances beyond our control, including technical issues in the execution process, shortage of labour during the construction period, and financial difficulties faced by the developer. These unavoidable challenges have caused delays in timely completion of the project.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Feb 2024
- Floors
- 8
- Unit mix
- 28 res ยท 7 comm
- Architect
- Makarand Ittam
- Plot / CTS / survey no.
- S. No./Gat No. 27/1A/1 (P), Near Nimbalkar Nagar, Opp to Tata Steel Yard, Tathawade, Tal Mulshi, Dist. Pune 411033
- Planning authority
- Pimpri Chinchwad Municipal Corporation
- Approved layout land
- 1,700 sq.m
- Land for this registration
- 1,700 sq.m
- Permissible built-up area
- 1,396.71 sq.m
- Registered office
- Alankar Niwas
- North
- By remaining property fromSurvey No 27
- South
- By remaining property fromSurvey No 27
- East
- By Road and Survey No 25
- West
- By remaining property fromSurvey No 27
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF BARODA โ 3441IFSC BARB0AKURDINEW ADMINISTRATIVE BUILDING PCNTDA NEAR AKURDI RAILWAY STATION AKURDI PUNE MAHARASTRA 411044
Commencement Certificate documents
- Commencement Certificate.pdf
- Commencement.pdf
- Commencement.pdf
- Commencement.pdf
- Commencement.pdf
Buyer community
Connect with other buyers and owners of Audumbar Green A Wing โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Audumbar Green A Wing. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.