THE SKYLARKMahaRERA P52100054899

by MOHISHA REALTORS LLP

Survey No. 94/1, Kiwale, 412101

Jun 2027
Possession
51.6%
Built
0
Complaints
456
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100054899
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
51.6% complete
Units sold
258 of 456

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2024
Floors
21
Unit mix
456 res ยท 0 comm
Architect
Kimaya Associates

Buyer community

Connect with other buyers and owners of THE SKYLARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE SKYLARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.