Under construction
JALASAMPADAMahaRERA P52100055301
by PARAM NILAY CONSTRUCTIONS LLP
TPS NO 1, F P NO 1/3, ERANDWANA, PUNE 411004, ERANDWANA, 411004
Nov 2027
Possession
20%
Built
0
Complaints
14
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100055301
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2027originally November 2026
- Construction
- 20% complete
- Units sold
- 0 of 14
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Building & registration
- RERA registered
- Mar 2024
- Floors
- 7
- Unit mix
- 14 res ยท 0 comm
Buyer community
Connect with other buyers and owners of JALASAMPADA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching JALASAMPADA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.