Under construction

UNIQUE SKY LINKS PHASE IMahaRERA P52100055408

by Aryan Housing

S. No. 135/1/1, CTS No. 2311, Pashan, 411021

Jun 2027
Possession
65.5%
Built
0
Complaints
117
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100055408
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
65.5% complete
Units sold
53 of 117

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Mar 2024
Floors
17
Unit mix
117 res ยท 0 comm
Architect
Anish Damodar Tambe

Buyer community

Connect with other buyers and owners of UNIQUE SKY LINKS PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UNIQUE SKY LINKS PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.