Under construction
SWAMI CLASSICMahaRERA P52100055551
by SAI IDEAL PROMOTERS AND DEVELOPERS
GAT NO 47 (P) OLD GAT NO 48 (P), TUPE WASTI, 412105
Mar 2027
Possession
89.4%
Built
0
Complaints
42
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100055551
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2025
- Construction
- 89.4% complete
- Units sold
- 1 of 42
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Building & registration
- RERA registered
- Apr 2024
- Floors
- 9
- Unit mix
- 42 res ยท 0 comm
- Architect
- Vision Associates
Buyer community
Connect with other buyers and owners of SWAMI CLASSIC โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SWAMI CLASSIC. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.