PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI MUKTAI PARADISEMahaRERA P52100055559

by Sai Muktai Associates

Gat No 193/2 Part, Jalochi, 413102

Mar 2027
Possession
30%
Built
0
Complaints
58
Units
Caution
  • Behind schedule. Possession is due Mar 2027 but construction is only at 30%.

Official RERA facts

Registration
P52100055559
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
30% complete
Units sold
3 of 58

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2024
Floors
6
Unit mix
48 res ยท 10 comm

Buyer community

Connect with other buyers and owners of SAI MUKTAI PARADISE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI MUKTAI PARADISE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.