PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Zambare IconMahaRERA P52100056059

by Shreeshivtej Buildcon Pvt. Ltd.

131/A/2/1, Jalochi, 413102

Jun 2027
Possession
22.7%
Built
0
Complaints
10
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 22.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100056059
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
22.7% complete
Units sold
0 of 10

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2024
Floors
10
Unit mix
0 res ยท 10 comm
Architect
Borade & Associates

Buyer community

Connect with other buyers and owners of Zambare Icon โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Zambare Icon. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.