PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Apex Commerce ZoneMahaRERA P52100056343

by Privis Realtors LLP

Survey No - 104/1/1 Part, Haveli - Village Baner, 411045

Apr 2027
Possession
10.9%
Built
0
Complaints
35
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 10.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P52100056343
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
10.9% complete
Units sold
10 of 35

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2024
Floors
5
Unit mix
0 res ยท 35 comm

Buyer community

Connect with other buyers and owners of Apex Commerce Zone โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Apex Commerce Zone. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.