Under construction

G S Crown PlazaaMahaRERA P52100056495

by G S Developers

Gat No. 90/1/Plot No 398, Haveli, Pune, 412207

Dec 2026
Possession
42.7%
Built
1
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 42.7%.

Official RERA facts

Registration
P52100056495
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
42.7% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2024
Floors
4

Buyer community

Connect with other buyers and owners of G S Crown Plazaa โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching G S Crown Plazaa. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.