Under construction

NYATI EMBLEMMahaRERA P52100076789

by NYATI CONSTRUCTION PRIVATE LIMITED

SURVEY NO 86/1/1/2, CTS NO 2024, PARVATI, PUNE 411009, Parvati, 411009

Dec 2027
Possession
29%
Built
2
Complaints
42
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100076789
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
29% complete
Units sold
19 of 42

RERA complaint record2 records

  • ComplaintSM1260044329 Jun 2026
    Ram Gawali vs NYATI CONSTRUCTION PRIVATE LIMITED
  • ComplaintSM1260018323 Mar 2026
    Ram Gawali vs NYATI CONSTRUCTION PRIVATE LIMITED
    Case No SM126000183.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2024
Floors
22
Unit mix
42 res ยท 0 comm
Architect
MANOJ TATOOSKAR

Buyer community

Connect with other buyers and owners of NYATI EMBLEM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NYATI EMBLEM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.