PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

NIRMAN ANAMIKAMahaRERA P52100076906

by NIRMAN DEVELOPERS

S NO 721/1 AND S NO 725/2 SUB PLOT NO 6/A F P NO 1000, SADASHIV PETH, 411030

Dec 2027
Possession
48.6%
Built
1
Complaints
28
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100076906
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
48.6% complete
Units sold
1 of 28

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2024
Floors
8
Unit mix
28 res ยท 0 comm
Architect
PRAKASH KULKARNI prakash kulkarni

Buyer community

Connect with other buyers and owners of NIRMAN ANAMIKA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIRMAN ANAMIKA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.