PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Aeternaa - C Wing Phase 1MahaRERA P52100077052

by KORELH REALLTECH LLP

S. No. 16/4B/6A/1, 16/3B/4A, 16/4B/6A, CTS No. 3565(P), 2837(P), 2838(P), Village Thergaon, Taluka Mulshi, District Pune 411033., Gujar Nagar, 411033

Dec 2028
Possession
27.3%
Built
0
Complaints
76
Units
Caution
  • Possession delayed ~1 yr. Originally promised Dec 2027, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52100077052
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2027
Construction
27.3% complete
Units sold
52 of 76

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2024
Floors
7
Unit mix
76 res ยท 0 comm
Architect
I.P. Associates

Buyer community

Connect with other buyers and owners of Aeternaa - C Wing Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aeternaa - C Wing Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.